A project you have contracted is subject to CEQA. What steps can you expect in the CEQA process and how do they impact the project?

a. The lead agency will examine project to see if it qualifies for a categorical or statutory exemption. If so they may issue a notice of exemption.

b. If not exempt the lead agency performs an initial study to determine if the project will have any significant negative impacts on environmental quality. If no the lead agency will issue a negative declaration. The lead agency may also issue a negative declaration with mitigation measures.

c. If the initial study indicates potential negative environmental impacts the lead agency will order an environmental impact report. This report will study the impacts in more detail and suggest mitigating measures if any to reduce the effects.