1. Subcontractor: File 20-day Preliminary Notice with county recorder, then within 30 days of Notice of Completion must file Claim of Lien. Then within 90 days a foreclosure action can be taken
2. Sub on public project: Serve Stop Notice within 30 days of Notice of completion, then file an action on the stop notice within 90 days of notice.
3. Prime Contractor: Within 10 days of completion, file Notice of Completion. Within 60 days of that, file Claim of Lien. Within 90 days of that file a Lien Foreclosure Action